Energy and transportation both appear among the capability areas identified in The Plan for a Stronger Canada, the national security strategy released on 29 October 2026, alongside critical minerals, defence, emerging technologies, food security and others. Federal investment in major infrastructure and domestic manufacturing has been directed accordingly, and Buy Canadian procurement prioritises domestic suppliers and materials in large federal construction contracts.

The firms that actually deliver this work — fabricators, electrical and mechanical contractors, equipment suppliers, module builders, specialist transport and installation companies — face a financing profile determined not by demand but by how infrastructure projects pay.

Why Infrastructure Supply Is Hard to Finance

Several characteristics compound in this sector:

A supplier can be profitable on every project and still face a liquidity position that deteriorates as its order book grows — because each additional project extends the period over which capital is committed.

Financing the Build Cycle

Progress and milestone receivables

Certified progress payments and approved milestone invoices are financeable. Certification matters: it converts work performed into a documented obligation a funder can advance against. Where the obligor is a utility, Crown corporation, government department or investment-grade developer, the credit supporting that receivable is strong, and pricing should reflect it. Where a buyer operates an early payment program, approved invoices can be drawn early without the supplier taking on debt — the structure applied by OAKRG's Canadian Supply Chain Performance Program across energy, transportation, manufacturing, defence, critical minerals and food production.

Holdback and retention

Accumulated holdback across concurrent projects is frequently a supplier's largest trapped asset, and it is often larger than any facility a lender would otherwise extend. Where available, replacing cash holdback with a surety instrument releases that capital immediately, and holdback receivables themselves can be financed in some structures.

Long-lead procurement

Purchase order and contract finance funds major equipment and material purchases against the underlying contract rather than the supplier's balance sheet. Supplier and vendor credit programs can carry part of the requirement, and equipment finance applies where the item being purchased is itself an asset. Our overview of vendor finance covers these arrangements.

Work in progress and inventory

Fabrication in progress is inventory, and an asset-based facility with an inventory component can advance against it — subject to the funder's ability to verify and value partially completed work, which requires sound job costing and progress measurement.

The order book is not the constraint. The constraint is how long capital stays committed before a holdback is released.

Capacity Investment Ahead of Award

Suppliers pursuing larger infrastructure packages frequently need capability before they can bid for it — larger fabrication bays, heavier lifting capacity, additional welding or testing certification, expanded yard and storage. Owners and engineering contractors increasingly want evidence of capacity before award, which means the investment precedes the contract justifying it.

This is term capital, not working capital: equipment and facility finance amortised over asset life, real estate debt or sale-leaseback on owned facilities, and subordinated debt or growth equity where the step change exceeds what asset-backed lending supports. Funding capacity expansion from an operating line is a recurring error that leaves the supplier unable to fund the production the new capacity was built for.

Bonding and Prequalification

Infrastructure work is bonded work, and surety capacity frequently binds before cash does. Sureties assess working capital and tangible net worth rather than backlog or profitability, so a supplier with a strong pipeline can be unable to bid because existing bonds have absorbed its capacity.

The remedies are balance sheet remedies: properly subordinated debt that sureties credit as equity for capacity purposes, reviewed or audited percentage-of-completion statements from an accountant the surety market recognises, removal of related-party receivables, and a documented record of accurate job cost forecasting. Our guide to mobilization, surety and contract finance sets out the mechanics.

Structuring for a Long Order Book

Suppliers winning repeatedly in this sector eventually need a capital structure rather than a series of facilities. In practice that means a revolving facility sized against receivables and work in progress that grows with volume, term debt matched to facility and equipment investment, a surety relationship with headroom for the bid pipeline, participation in buyer early payment programs where they exist, and purchase order finance available for individual large packages.

Equity investors are also active in this part of the market, and they pay most for suppliers with contracted multi-year revenue from creditworthy counterparties, demonstrated margin discipline across completed projects, specialised capability that limits competition, and management depth beyond the founder. Contracted utility, Crown and government revenue is among the strongest characteristics an investor can underwrite, because the counterparty does not default.

OAKRG works with Canadian energy and transportation suppliers and contractors across receivables and early payment facilities, purchase order and contract finance, equipment and facility capital, subordinated capital for bonding and growth equity — through its energy project finance and supply chain finance practices, with transactions typically from $1M to $100M+.

Frequently Asked Questions

Can construction holdbacks be financed in Canada?

In several forms, yes. Holdback receivables can be financed directly under some facilities, though funders assess them carefully because release depends on project completion and the expiry of lien periods. The more effective route where it is available is to replace cash holdback with a surety instrument, which substitutes a bond for withheld cash and releases that capital immediately. For a supplier carrying holdback across several concurrent projects, the accumulated balance is frequently larger than any external facility on offer, which makes this one of the most overlooked sources of liquidity in the sector.

How do suppliers fund long-lead equipment purchases?

Through capital underwritten on the contract rather than the balance sheet. Purchase order and contract finance advances against the confirmed order so the supplier can place and pay for long-lead items such as transformers, switchgear or specialist steel, with repayment from the resulting milestone or delivery invoice. Vendor and supplier credit programs can carry part of the requirement, and where the long-lead item is itself an asset with resale value, equipment finance may apply. Each of these is generally more accessible than an increase in a bank operating line for the same purpose.

What is the difference between financing work in progress and financing receivables?

A receivable exists once work has been certified or an invoice approved, which gives the funder a documented obligation from an identifiable payer to advance against. Work in progress is value created but not yet billed, so there is no obligation yet and the funder must instead verify and value partially completed work. That makes work-in-progress financing harder to obtain, more dependent on reliable job costing and progress measurement, and generally available at lower advance rates. Suppliers with strong project accounting access it; those without usually cannot.

Why does surety capacity constrain infrastructure suppliers more than cash?

Because bonding is a prerequisite for bidding, and sureties assess working capital and tangible net worth rather than backlog or profitability. A supplier whose existing bonds have absorbed its assessed capacity cannot bid for further work regardless of how much cash it holds or how strong its pipeline is. Capacity is increased by improving the balance sheet metrics the surety tests — most effectively through properly subordinated debt, which many sureties credit as equity for capacity purposes, and through upgraded percentage-of-completion financial reporting from an accountant the surety market recognises.