Construction is one of the few industries in which winning is dangerous. A contractor awarded a project substantially larger than its usual scope must mobilise crews and equipment, procure long-lead materials, post bonds, and fund payroll and subcontractors for the first 60 to 120 days — all before the first progress payment clears, and with 5 to 10 per cent of every subsequent payment withheld as retention until the project is complete.
The capital requirement is therefore front-loaded against a revenue stream that is back-loaded. Contractors who treat this as a single working capital problem and solve it with an overdraft tend to run out of capacity at exactly the point where their pipeline is strongest. The requirement is better understood as four distinct problems.
Problem One: Mobilization
Mobilization costs — moving equipment to site, establishing site facilities, initial crews, bonds and insurance, long-lead procurement — are incurred in the first weeks and recovered over the life of the contract. Several instruments address this directly:
- Negotiated mobilization advance. The simplest solution and the most frequently overlooked. Many owners and general contractors will fund an advance of 5 to 15 per cent of contract value against a bond, recovered pro rata from progress payments. It costs nothing but negotiating effort, and it should be requested before the contract is signed rather than after cash is tight.
- Contract-specific working capital facility. A facility sized against the awarded contract and repaid from its progress payments, ring-fenced from the contractor's other obligations.
- Equipment finance or short-term rental for project-specific plant, so that equipment needs do not consume the cash required for payroll.
- Supplier and vendor terms on long-lead materials, which effectively transfers part of the financing to the supply chain. Our overview of vendor finance covers how these programmes are structured.
Problem Two: Bonding Capacity
For contractors working on public projects or for large private owners, surety capacity is frequently a harder constraint than cash. A surety underwrites three things: character, capacity and capital. The capital test is the one most often failed, and it is assessed on working capital and tangible net worth rather than on profitability or backlog.
This produces a specific trap. A contractor can hold a strong pipeline and be unable to bid, because every available bid is already committed under existing bonds. Increasing surety capacity requires improving the balance sheet metrics the surety tests:
- Working capital as the surety calculates it, which typically excludes related-party receivables, under-billings beyond a threshold, and inventory of limited realisable value.
- Tangible net worth, excluding intangibles and goodwill.
- Quality of financial reporting. A reviewed or audited statement prepared on the percentage-of-completion basis by an accountant known to the surety market materially improves available capacity, often more than an equivalent amount of additional equity.
- Work-in-progress schedule accuracy. Sureties examine job-by-job gross profit history and the variance between estimated and final margins. A pattern of margin erosion on completed jobs reduces capacity regardless of balance sheet strength.
Subordinated debt deserves particular attention here, because sureties will often treat properly subordinated debt as equity for capacity purposes. A relatively modest subordinated facility can therefore unlock a multiple of its value in additional bonding capacity — one of the highest-leverage financing moves available to a growing contractor.
For a contractor, the binding constraint is rarely the next project. It is the balance sheet the surety reads before allowing a bid at all.
Problem Three: Progress Payments and Retention
Progress billing in construction is slow by design. Applications are submitted, certified, approved and paid across a cycle commonly running 45 to 90 days, with retention withheld throughout. A contractor running several projects simultaneously carries a substantial receivable at all times, plus accumulated retention that may not be released until well after practical completion.
Both are financeable. Receivables facilities can be structured against certified progress payments, where certification provides the documentation a lender requires. Retention itself can be financed in some markets, or replaced entirely by a retention bond, which substitutes a surety instrument for withheld cash and releases that capital back into the business. For contractors with persistent retention balances across multiple projects, replacing retention with bonds can release more working capital than any external facility.
The mechanics of financing against certified receivables are set out in our overview of accounts receivable financing.
Problem Four: Paying the Supply Chain
Main contractors sit between owners who pay slowly and subcontractors who need paying promptly. Squeezing subcontractor terms is the traditional response and a costly one: it raises subcontractor pricing, loses access to the best trades, and in several jurisdictions now conflicts with prompt payment legislation.
Supply chain finance resolves the tension without either party funding it from their own balance sheet. The main contractor keeps its payment terms; the subcontractor draws early payment against approved applications at a cost based on the main contractor's credit rather than its own. Our guides to reverse factoring and early payment programs explain both sides of the structure.
Raising Growth and Acquisition Capital
Contractors seeking to grow beyond what working capital facilities support have several routes, each with different consequences for control:
Subordinated or mezzanine debt
Frequently the best fit, because it strengthens the balance sheet for surety purposes while leaving ownership intact. More expensive than senior debt and cheaper than equity.
Minority growth equity
Suitable where the business is pursuing a step change — new geography, new discipline, major equipment programme — that working capital instruments cannot fund. Investors in construction concentrate on backlog quality, margin consistency and whether the business depends on individual relationships.
Acquisition finance
For contractors buying capability or geography, typically combining debt supported by the target's cash flow with equity covering the balance and integration costs.
Equity investors in construction are more cautious than in most sectors, for a defensible reason: the industry carries fixed-price risk on long-duration contracts with thin margins, and a single disputed project can absorb several years of profit. They pay most for contractors with repeat institutional clients, diversified project types, demonstrated margin discipline across the cycle, and management depth that does not depend on the founder's personal relationships.
OAKRG works with contractors and construction businesses across mobilization and contract finance, subordinated capital for bonding, receivables and retention facilities, supply chain programmes and growth equity, with transactions typically from $1M to $100M+.
Frequently Asked Questions
How can a contractor increase its bonding capacity?
By improving the metrics the surety tests, which are working capital and tangible net worth rather than profitability or backlog. The highest-leverage moves are usually adding properly subordinated debt, which many sureties credit as equity for capacity purposes; upgrading to reviewed or audited percentage-of-completion financial statements prepared by an accountant the surety market recognises; cleaning related-party receivables off the balance sheet; and demonstrating accurate job cost forecasting with consistent final margins. A modest subordinated facility frequently unlocks several times its value in additional capacity.
Can a contractor finance mobilization costs on a new contract?
Yes, and usually in more than one way. The first step is to negotiate a mobilization advance with the owner or general contractor, commonly 5 to 15 per cent of contract value against a bond and recovered from progress payments, which is the cheapest option and is often simply not requested. Beyond that, a contract-specific working capital facility sized against the awarded contract, equipment finance for project plant, and extended supplier terms on long-lead materials each cover part of the requirement. The advance should be negotiated before the contract is signed.
Is retention financing available, and is it worth it?
In several markets, yes. Retention can sometimes be financed directly, but the more effective route is usually to replace cash retention with a retention bond, substituting a surety instrument for withheld cash and releasing that capital immediately. For a contractor carrying retention across several concurrent projects, the accumulated balance is often larger than any facility an external lender would offer, which makes this one of the most overlooked sources of working capital in the sector.
Why are equity investors cautious about construction businesses?
Because the sector combines fixed-price risk on long-duration contracts with structurally thin margins, meaning a single disputed or loss-making project can consume several years of profit. Investors respond by paying premiums for the characteristics that reduce that risk: repeat institutional clients rather than one-off awards, diversity across project types and geographies, documented margin consistency through a full cycle, and management depth that does not rest on the founder's personal relationships. Contractors that can evidence those four things are valued very differently from those that cannot.